Griffy dam trail crossing gets OK from Bloomington RDC: “It’s not within the TIF—it’s serving the TIF.”

A gravel path across the top of Griffy dam, including staircase access and safety fencing, with an estimated cost of $375,000, now has approval in concept as a Bloomington redevelopment commission project.

The unanimous vote by the five-member Bloomington RDC came at the group’s regular meeting on Monday. No expenditure of funds was approved with Monday’s vote.

It’s currently possible for hikers to get across the dam by going through a fence, Bloomington parks operations manager Tim Street told the RDC. But the new path will “formalize” the crossing and in places improve the aesthetics of chain link with cedar split rail fence.

The Griffy dam trail crossing is on the list of projects approved by the Bloomington city council and the board of park commissioners in May this year, as part of a $10-million bond package. Half that amount was was made up of parks bonds.

When Bloomington’s city council gave its approval for issuance of the parks bonds, it put the dam crossing last on in its priority ranking.

The low priority ranking by the city council is key to the RDC’s agreement now to make the dam crossing one of its projects to be paid for out of tax increment finance (TIF) revenue. Continue reading “Griffy dam trail crossing gets OK from Bloomington RDC: “It’s not within the TIF—it’s serving the TIF.””